| Yard | The 35.5-metre-high grain silo with 19 interior grain chambers has space for 2 800 tonnes of grain. The grain silo was built in 24-hour operation. Construction took a total of 212 hours, or just under nine days. |
|---|---|
| Location | Hallau, Switzerland |
| Subcategory | SILOS |
| Application | The new construction of the additional grain silo in Hallau was built in 24-hour operation. The building was erected using slipforming, which was raised in three-minute cycles. |
| Start and finish date | 2022 |
| Application Type | Concrete restoration |
| Installer companies | KIBAG Beton AG |
| Specialists involved | Neumühle Hallau GmbH |
| MAPEI Coordination | Reto Märki |