Područje zahvata | The 35.5-metre-high grain silo with 19 interior grain chambers has space for 2 800 tonnes of grain. The grain silo was built in 24-hour operation. Construction took a total of 212 hours, or just under nine days. |
---|---|
Lokacija | Hallau, Switzerland |
Podkategorija | SILOS |
Opis izvođenih radova | The new construction of the additional grain silo in Hallau was built in 24-hour operation. The building was erected using slipforming, which was raised in three-minute cycles. |
Datum početka i završetka | 2022 |
Vrsta radova | Obnova betonskih objekata |
Izvođač radova | KIBAG Beton AG |
Voditelj projekta | Neumühle Hallau GmbH |
MAPEI koordinator | Reto Märki |