| "Yard" | Pillar at Km 8+500 of Grotte Orientali |
|---|---|
| "Location" | Rutigliano - Contrada Caggiano, Italy |
| "Subcategory" | BRIDGE |
| "Application" | supply of products for repairing of concrete pillar, of the pulvino and rubber joints |
| "Start and finish date" | 2018 |
| "Application Type" | Concrete restoration, Structural reinforcement |
| "Owner" | Città metropolitana di Bari |
| "Contractor company" | SCEAP |
| "Installer companies" | SCEAP |
| "Architects" | ing. Oronzo Pannarale |
| "Project Manager" | ing. Rita Monaco |
| "MAPEI Distributor" | Particolori srl |
| Project Manager | Ing. Michele Fazio |
| "마페이 조정" | ing. Dispoto Giammario - Divisione Grandi Progetti Mapei SpA; Marcuccio Antonello |
Mapei Korea
46, 5sandan 6-ro, Susin-myeon, Dongnam-gu, Cheonan-si, Chungcheongnam-do, Korea
- Fax +82 41 566 8858