| Yard | The 35.5-metre-high grain silo with 19 interior grain chambers has space for 2 800 tonnes of grain. The grain silo was built in 24-hour operation. Construction took a total of 212 hours, or just under nine days. |
|---|---|
| Locație | Hallau, Switzerland |
| Sub-categorie | SILOZ |
| Aplicație | The new construction of the additional grain silo in Hallau was built in 24-hour operation. The building was erected using slipforming, which was raised in three-minute cycles. |
| Data de început și de finalizare | 2022 |
| Tipul aplicației | Reabilitare structuri beton |
| Societăți de instalare | KIBAG Beton AG |
| Manager de proiect | Neumühle Hallau GmbH |
| Coordonare MAPEI | Reto Märki |