| Pátio | tennis courts and netball courts |
|---|---|
| Local | Ascot Vale (Melbourne), Australia |
| Subcategoria | GOLF CLUB, CAMPO DE TÉNIS |
| Aplicação |
Installation of Mapecoat System on tennis courts and netball courts
Surface Preparation sequence; • Clean and prep new concrete bases post 28 days curing using a combination of mechanical (diamond) grinding and high-pressure water blasting. Surfacing System sequence; • Apply ‘Mapecoat I 600 W Primer’ to courts. • Minor patching & levelling of new concrete surface as required using Mapecoat TNS White Base Coat • Apply ‘Mapecoat TNS Finish 1 – Velocity Blue’ to the centre of courts. (First ‘finish’ coat) • Apply ‘Mapecoat TNS Finish 1 – Velocity Blue’ to the centre of courts. (Second ‘finish’ Coat) • Apply ‘Mapecoat TNS Finish 1 – True Blue’ to the perimeter of courts. (First ‘finish’ Coat) • Apply ‘Mapecoat TNS Finish 1 – True Blue’ to the perimeter of courts. (Second ‘finish’ Coat) • Apply ‘Mapecoat TNS White Lines’ for tennis to courts. • Apply ‘Mapecoat TNS Yellow Lines’ for netball to courts. |
| Datas inicial e final | 2019 |
| Tipo de aplicação | Soluções para pavimentação desportiva, Preparação da superfície |
| Proprietário | Tennis and Netball Centre |
| Empresa empreiteira | Turf One Pty Ltd |
| Empresas instaladoras | King of Courts Pty Ltd |
| Project Manager | Moonee Valley City Council |
| Coordenação da MAPEI | Nicolas Cheal |