Podrobnosti | The 35.5-metre-high grain silo with 19 interior grain chambers has space for 2 800 tonnes of grain. The grain silo was built in 24-hour operation. Construction took a total of 212 hours, or just under nine days. |
---|---|
Lokacija | Hallau, Switzerland |
Kategorija | SILOS |
Opis opravljenih del | The new construction of the additional grain silo in Hallau was built in 24-hour operation. The building was erected using slipforming, which was raised in three-minute cycles. |
Datum začetka in konca | 2022 |
Več o projektu | Obnova betona |
Podizvajalec | KIBAG Beton AG |
Vodja projekta | Neumühle Hallau GmbH |
Koordinacija MAPEI | Reto Märki |