| Područje primene | The 35.5-metre-high grain silo with 19 interior grain chambers has space for 2 800 tonnes of grain. The grain silo was built in 24-hour operation. Construction took a total of 212 hours, or just under nine days. |
|---|---|
| Lokacija | Hallau, Švajcarska |
| Kategorija objekta | SILOS |
| Radovi izvedeni Mapei materijalima | The new construction of the additional grain silo in Hallau was built in 24-hour operation. The building was erected using slipforming, which was raised in three-minute cycles. |
| Vreme izvođenja radova | 2022 |
| Vrsta radova | Sanacija betona |
| Podizvođač | KIBAG Beton AG |
| Projektant | Neumühle Hallau GmbH |
| Mapei koordinatori | Reto Märki |